Bondi Beach
Phase two of the Bondi project included a terrace area with a Gym underneath, there was leaks from the terrace to the gym.
The client organised the terrace back to the substrate and we carried out the following;
Schedule of works:
Clean and removed all waste from the substrate.
Prime the substrate.
Torch on 1st coat of Soprema 3.0S membrane.
Torch on 2nd coat of Soprema 4AR mineral.
Paint Alsan flashing throughout the terrace.